← Jobs
Liberty Senior Living — Phase 2
J-1040Liberty Senior Living · Voorhees, NJ
Waiting On GcTape
Assisted-living wing, fire-rated assemblies.
Contract
Original Contract
$47,000
Approved COs
$0
Current Contract
$47,000
Pending COs
$0
Labor
Estimated Hours
430 hrs
Actual Hours
210 hrs
Labor Variance
-51.2%
Actual Labor Cost
$9,450
Materials & Projection
Est. Material
$11,000
Actual Material
$5,400
Projected Cost
$30,350
Projected Margin
35.4%
Projected profit $16,650 on a current contract of $47,000 · target margin 24%.