Saturday, June 13

Sunrise Hotel Renovation · Mike Crew · Clear, 69°F
Workers
3
Total Hours
24 hrs
Phase
Finish

Work Completed

Finished guest rooms 204–212.

Delays

Cement board delivery arrived late morning.

Crew on Site

  • Mike SullivanForeman8 hrs
  • Pavel KowalskiFinisher8 hrs
  • Wes TurnerHanger8 hrs

Submitted by Mike Sullivan