Saturday, June 13
Sunrise Hotel Renovation · Mike Crew · Clear, 69°F
Workers
3
Total Hours
24 hrs
Phase
Finish
Work Completed
Finished guest rooms 204–212.
Delays
Cement board delivery arrived late morning.
Crew on Site
- Mike SullivanForeman8 hrs
- Pavel KowalskiFinisher8 hrs
- Wes TurnerHanger8 hrs
Submitted by Mike Sullivan