Friday, June 12
Oak Street Office Fit-Out · Luis Crew · Rain, 64°F
Workers
3
Total Hours
24 hrs
Phase
Finish
Work Completed
Final sand conference rooms, prepped for paint.
Crew on Site
- Luis OrtegaForeman8 hrs
- Hector SalinasTaper8 hrs
- Diego FloresFinisher8 hrs
Submitted by Luis Ortega