Sunday, June 14
Maple Apartments — Units 1–12 · Jose Crew · Clear, 72°F
Workers
5
Total Hours
40 hrs
Phase
Hang
Work Completed
Hung board in Units 5–8. Stocked Units 9–12 for tomorrow.
Delays
Elevator unavailable ~2 hrs — material had to be carried up the stairwell.
Issues
Building access window tighter than planned; coordinating with property manager.
◆ Extra Work Found — Not in Original Scope
GC requested soffit drywall in Unit 7 to box out new HVAC run — not in original scope. Roughly 40 labor hours + board/bead. Needs a change order.
Crew on Site
- Jose RamirezForeman8 hrs
- Carlos MendezHanger8 hrs
- Diego FloresFinisher8 hrs
- Tomas RiveraHanger8 hrs
- Andres PenaHanger8 hrs
Submitted by Jose Ramirez