Sunday, June 14

Lincoln Medical Center · Mike Crew · Humid, 80°F
Workers
3
Total Hours
24 hrs
Phase
Finish

Work Completed

Skim coat east corridor, sanded exam rooms 1–6.

Issues

High humidity slowing mud cure; running fans overnight.

Crew on Site

  • Mike SullivanForeman8 hrs
  • Pavel KowalskiFinisher8 hrs
  • Wes TurnerHanger8 hrs

Submitted by Mike Sullivan